
Woods Hole Terminal Reconstruction Project
To receive weekly email updates about the terminal reconstruction project, please visit our eNews provider, GovDelivery, and subscribe! Click here to sign up.
To report concerns about construction or environmental issues concerning the Woods Hole Terminal Reconstruction Project. Please call 508-289-4419 to be connected with either Bill Cloutier or another Authority staff member, should you have a concern that needs immediate attention. As always, you can also email Bill at [email protected] or call his office during work hours at 508-548-5011, ext. 429.
Week ending January 27, 2023
THIS WEEK, Lawrence-Lynch Corp. completed the installation of the stormwater drainage in the Phase 5D work site. The weather this past week has slowed the work progress.
NEXT WEEK, Lawrence-Lynch will start bringing in fill material to raise the worksite elevation. The elevation will be raised to elevation +9 feet, tapering to elevation +6 feet at the back of the worksite.
Week ending January 20, 2023
THIS WEEK, Lawrence-Lynch Corp. completed the demolition in the current work site and started the installation of the stormwater structures.
NEXT WEEK, Lawrence-Lynch will continue with the installation of the new stormwater system.
Week ending January 13, 2023
THIS WEEK, Lawrence-Lynch Corp. set up the work site in Phase 5D, which consists of most of the vehicle staging lanes. They milled all the asphalt in the work area and started demolition of the old sewer pump out tanks and piping.
NEXT WEEK, Lawrence-Lynch will continue with the demolition of the old sewer pump out system and start installing the new stormwater system.
Week ending January 6, 2023
THIS WEEK, Lawrence-Lynch Corp. finished raising the grade of the Phase 5C work site. They were scheduled to pave the work site with the asphalt binder course on Friday.
NEXT WEEK, Lawrence-Lynch will set up the Phase 5D work site that encompasses most of the staging lanes. They will remove the old sewer pump-out underground tanks and start removing the asphalt in the staging area. It is expected that this phase of work will last four to five weeks.
Phase 5 landside work
The scope of work for this phase focus on preparing the site for the building construction. The electricians will set up a temporary switchgear building in the employee lot so power can be moved from the freight shed. Lawrence Lynch will be raising the base elevation approximately 5 feet to satisfy the flood plain requirements, and they will be installing new stormwater piping for the back side of the property. This piping will connect with the stormwater piping that was installed as part of the marine contract. Raising the site elevation is complicated logistically because the site must stay in operation during the construction. We plan to complete the elevation work by moving the construction work zone six different times. This will allow vehicle access to at least two vessel slips at all time and continue to have staging available at the site.
Click here to download maps of the six subphases of the project (updated 1/13/2023).
Click here for videos of the Schematic Design and Design Development public engagement sessions.
January 19, 2022 Community Engagement Session Presentation
November 4, 2021 Landside Community Update presentation
July 7, 2021 Landside Design Presentation
Landside Design Community Forum (updated 3/23/2021)
Related project documents
Chapter 91 license - recommended final decision
Falmouth Conservation Commission Order of Conditions
Environmental Notification Form (WARNING: large file)